Tank Installation & Compliance

KpH Environmental provides a total tank installation and compliance service - from the initial survey through to full installation and commissioning. This includes tank supply, repair, routine maintenance and full compliance surveys.

Tank Installation Services

KpH offers a complete interior strip out, enabling works and demolition package.

View our Tank Installation Services...

  • Supply and installation of plastic or steel bunded tanks
  • Commissioning of tank installations
  • Tank repair and fabrication works
  • Installation of tank contents and gauging systems
  • Installation of high/low level and bund alarms
  • Installation of valves, filters and fire sensors
  • Installation of overfill prevention devices and offset fill points
  • Product/fuel uplift, transfer and disposal
  • Temporary tank supply
  • Bulk storage tank hire
  • Tank design and bespoke construction
  • Pipe work alterations
  • Tank maintenance, painting and refurbishment
  • Plinth/base installation and modification
  • Bund installation, cleaning, maintenance, relining and repairs
  • Installation and commissioning of interceptors/cesspits
  • Installation of fire wall protection

Tank Surveys & Compliance Works

View our Tank Surveys & Compliance Works...

  • OFTEC registered inspections and compliance surveys
  • Full compliance reporting and remedial recommendation
  • Renewal/installation of tank contents and gauging systems
  • Renewal/installation of high/low level and bund alarms
  • Pipe work alterations and installation of valves and filters
  • Renewal/installation of overfill prevention devices and offset fill points
  • Bund cleaning, maintenance, relining and repairs
  • Hydrostatic/pressure tank and fuel line testing and reporting
  • Ultrasonic thickness inspection and reporting

Case Study 1 ⬍

Client – British Airways C/O Carillion
Project – Testing of Tanks and Upgrade of Fuel System, Heathrow Airport

Overview – KpH were contracted to test the existing five below ground fuel storage tanks, including fuel lines and upgrade the installation to meet current legislation. The tanks and fuel lines all passed test, however due to the age of the tank installation, the client instructed replacement of the existing steel pipework and upgrading the alarm and gauging systems.

It was essential the site remained operational, therefore a temporary oil supply line was installed to allow a continuous supply of oil at all times. The project went extremely smoothly with one unforeseen problem being encountered, in that whilst breaking out the concrete housing surrounding the pipework into the plant room, steel plates were encountered embedded within the concrete with the pipe work welded to the plates. On instruction from the client the plates were broken out and the pipework renewed and the internal manifold replaced.

The scope of works included:

  • Initial integrity testing of the 5 nr below ground fuel storage tanks, including all associated supply and fill lines
  • Installation of a temporary fuel supply line to allow the site to remain operational
  • Carefully breakout reinforced concrete to allow removal of pipework entering the plant room and tank chambers, prior to removal of the concrete templates were formed from plywood to ensure the new pipework would be installed in the identical positions
  • Remove unforeseen steel plates embedded in concrete and the manifold system within the plant room
  • Dismantling and removal of existing pipework from all five oil storage tanks
  • KpH’s in house expertise fabricated over 100 six metre lengths of 50mm steel barrel with mechanical flanges, each length was coated with rust preventer and pressure tested to 1.0 bar prior to leaving KpH’s fabrication workshop
  • Installation of 700 metres of new 50mm steel pipework, pressure test lines and commission
  • Reinstate manifold system within the plant room and fit new gaskets
  • Reinstate reinforced concrete within tank chambers and plant room using plywood shuttering templates taken earlier during the project
  • Upgrading of the system also included the relocation of the existing overfill alarm panel, to be extended and relocated within the fill point cabinet
  • The system also required the replacement of corroded capillaries to the gauging system

Case Study 2 ⬍

Client - H&S Aviation, Portsmouth Airport
Project - Tank testing and compliance works

H&S Aviation’s Jet A-1, aircraft fuel storage tank, required its five year maintenance and compliance survey. KpH was contracted to carry out these works and issue a full report, in accordance with current legislation for the storage of fuels in above ground vessels.

The scope of works included:

  • Transfer of 5,000-litres of Jet A-1 aviation fuel into a holding tanker
  • Confined spaces team to man, enter, clean and degas 44,038-litre Jet A-1 doubled skinned aviation fuel storage tank, disposing of residual product and the build up of sludge, to a licensed waste disposal facility
  • Jet wash and clean the bund, disposing of associated washings via vacuum tanker
  • Carry out visual inspection of tank surfaces, wealds, associated pipe work and fill point
  • Carry out ultrasonic thickness testing Transfer usable A-1 aviation fuel back into tank and refit man lid with new gasket
  • Issue compliance report with recommendations for any remedial works required to meet current legislation

 

Our OFTEC registered technicians install fuel, oil and chemical tanks, which range from a small bunded plastic/steel tank in a private dwelling, to multi-thousand litre commercial/industrial bulk installations.

Under current PPG2 oil storage regulations, periodic storage tank testing and inspection is essential to minimise the risk of tank failure and associated leakage, which can threaten operations, the environment and even life.

KpH provides OFTEC inspections and compliance surveys, providing a full report that identifies any non-conformance and remedial recommendations required.

Our highly skilled technicians can upgrade any installation to comply with current legislation. In more serious situations where tanks have failed, potentially causing an environmental incident, our experienced welders will repair or even replace leaking sections to bring the tank back into service.

Previous Projects

KpH recently worked on a major project for Johnson & Johnson at their global baby care facility based at High Wycombe, Buckinghamshire. The scope of works included the installation of a 30,000-litre bunded steel tank within the basement area.

The tank was specially fabricated in order to fit the tight dimensions of the basement; the tank weighed 6.2 tonnes and was craned to basement level then carefully positioned within the basement using rollers. Fuel within the 3 No. 40,000-litre under ground storage tanks was then transferred to the new tank in order for their removal to commence.

The removal process involved cleaning and de-gassing of the tanks, once made safe they were then excavated and disposed of to a licensed re-cycling facility. The excavations were then backfilled using suitable materials and the Johnson & Johnson impressive car park and grounds reinstated to their former glory. The work undertaken by KpH highlights the extensive resources at our disposal to undertake even the largest jobs.

Download
Service Information